dspTrack

Longest Running Tasks

Use this page while Viewing Reports in dspTrack™.

To access this page:

  1. Click Track > Reports in the Navigation pane.
  2. Click Longest Running Tasks.

Field

Description

PROJECT NAME

Displays the project name that contains the plan and task.

PLAN NAME

Displays the plan name that contains the task.

TASK NAME

Displays the task name.

TASK TOTAL HOURS

Displays the total number of hours worked for the task, based on the number of hours between the actual start and actual finish date if the task status is Completed, or the number of hours between the actual start date and the current date if the task is not in a Completed status.

PLAN TOTAL HOURS

Displays the total number of hours estimated to be worked in the plan based on the duration and UOM.

PERCENTAGE OF PLAN

Display the percentage of hours worked for the task compared to the total number of hours estimated to be worked in the plan.