dspTrack

Metrics By Tag

Use this page while Viewing Reports in dspTrack™.

To access this page:

  1. Click Track > Reports in the Navigation pane.
  2. Click Metrics By Tag.

Field

Description

TAG ID

Displays name of tag.

PLAN TASK ID

Displays name of plan task associated with the tag.

TASK DURATION HOURS

Displays total number of duration hours for the selected task, as entered on the Plan Task page.

NOTE: If a UOM other than days is used, dspTrack™ will convert this value to hours.

TOTAL TAG TASKS

Displays total number of tasks assigned to the tag.

TOTAL TAG DURATION HOURS

Displays the total number of duration hours for all tasks assigned to the tag.

PERCENTAGE OF TAG

Displays the percentage of duration hours for the selected task compared to the total duration hours for all tasks assigned to the tag.

PLANNED TIME SPAN HOURS

Displays the total planned time span hours for the task. Time span hours are the hours between the planned start date and time and the planned finish date and time.

ACTUAL TIME SPAN HOURS

Displays the actual planned time span hours for the task. Time span hours are the hours between the actual start date and time and the actual finish date and time.

PERCENTAGE OF PLANNED

Displays the percentage of planned time span hours for the selected task compared to the total time span hours for all tasks assigned to the tag.