dspTrack

Milestone Completion

Use this page while Viewing Reports in dspTrack™.

To access this page:

  1. Click Track > Reports in the Navigation pane.
  2. Click Milestone Completion.

Field

Description

PROJECT NAME

Displays the project name that contains the plan.

PLAN NAME

Displays the plan name that contains the task.

TASK NAME

Displays the task name marked as a milestone in an imported project file. Milestone tasks have the Milestone check box enabled on the Plan Task page’s Vertical View on the Additional Information tab.

TASK STATUS

Displays the task status, Ready, Waiting, In Progress or Completed.

PLANNED FINISH DATE

Displays the planned finish date for the task according to the project plan.

ACTUAL FINISH DATE

Displays the actual finish date for the task which may differ from the planned finish date.