dspTrack
Tasks Due Next Week
Use this page while Viewing Reports in dspTrack™.
To access this page:
- Click Track > Reports in the Navigation pane.
- Click Tasks Due Next Week.
Field |
Description |
PROJECT NAME |
Displays the project name that contains the plan. |
PLAN NAME |
Displays the plan name that contains the task. |
TASK NAME |
Displays the task name. |
TASK STATUS |
Displays the task status, Ready, Waiting, or In Progress. |
PLANNED START DATE |
Displays the planned start date for the task according to the project plan. |
PLANNED FINISH DATE |
Displays the planned finish date, occurring in the next week, for the task according to the project plan. |
ACTUAL START DATE |
Displays the actual start date for the task, which is the date a user clicked Next Action for the task on the Work List when the task was in Ready status. This may differ from the planned start date. |
DESCRIPTION |
Displays the task description. |