Master Data Management
Set a Scenario Role to Skip the Finish Event
When a request role’s conditions are not met, users can configure a setting at the scenario role level so that the Stewardship Tier does not run the Finish event.
Using the Quick Finish process, when a request role that uses this scenario role has conditions that are not met, the Stewardship Tier:
-
Sets dependencies complete for all dependent request roles
-
Logs the role finish in the Request Role Log
-
Calls an update procedure to determine if subsequent roles should be finished based on conditions
Using the Full Finish process, when a request role that uses this scenario role has conditions that are not met, the Stewardship Tier:
-
Creates a Finish job for that role that didn’t meet its conditions
NOTE: That Finish job runs the inherit validation processes and custom business rules for that role.
-
Logs that the role's conditions were not met in the Request Role Log
To set a scenario role to skip the Finish event:
-
Select Master Data Management > Design in the Navigation pane.
-
Click the Scenarios icon for a category.
-
Click the Roles icon for a scenario.
-
Click the Vertical View icon for a scenario role.
-
Check the Quick Finish check box.